Progress on the construction of Boatle-Game City road project to date is at 25 per cent against a planned 33 per cent target. Answering a question in Parliament, Minister of Transport and Communications Mr Kitso Mokaila said it was unlikely that the project would be completed on time and within the initially approved budget.
He said this was due to the late acquisition of burrow pits, late relocation of services at Boatle junction and at Kgale. “The contractor has already submitted a claim for extension of time with costs and this is currently being considered,” he said. Ramotswa MP Mr Samuel Rantuana had wanted the minister to state progress made in the construction of the Boatle-Game city road project and whether it would be completed on time and on the initially approved budget. Ends