Legal battle delays Kazungula Botswana Defence Force Camp project
19 Nov 2026
Construction of the new Kazungula Botswana Defence Force (BDF) camp remains stalled due to an ongoing court case involving the contractor and Botswana Housing Corporation (BHC).
Minister for State President, Defence and Security, Mr Moeti Mohwasa, told Parliament on Wednesday that the legal dispute had delayed the delivery of critical infrastructure intended to strengthen the BDF’s operational presence and logistical capacity in northern Botswana.
Responding to a question from Chobe Member of Parliament, Mr Simasiku Mapulanga, Mr Mohwasa said the project comprised three interdependent packages, with the implementation of the second and third packages dependent on the completion of the first. He explained that package one covered internal roads and the installation of electrical, water and sewerage reticulation, with BHC engaged as the contractor.
Package two comprised major facilities, including a hospital, mechanical workshop, clinic, Military Police facilities, kitchen, fuel station and barracks, intended to replace the existing facilities at Ferry Camp and Fairways. Package three, according to the minister, involved the construction of an office building and warehouse. Mr Mohwasa said the project commenced on January 20, 2020 and was initially scheduled for completion in April 2025.
However, works were interrupted following a contractual disagreement between BHC and Dan Holdings. He said Dan Holdings had sought an upward adjustment of the contract sum, arguing that the cost of the internal road network had been underestimated in its tender. BHC rejected the request, prompting the contractor to suspend works, citing financial constraints.
The dispute was subsequently taken to court, which ruled in favour of BHC. However, Dan Holdings appealed the ruling, and the matter remains before the courts.
Mr Mohwasa acknowledged that the dispute and ensuing legal proceedings had caused a regrettable delay, postponing the delivery of infrastructure required by the BDF and potentially increasing the overall project cost. He said government had to respect the judicial process and ensure that any further action complied with the law and contractual obligations to avoid prejudicing the proceedings or exposing public funds to additional liabilities. On the way forward, he said the BDF and BHC were monitoring the matter. Subject to the outcome of the appeal and applicable procurement requirements, BHC intended to assess completed and outstanding works, determine the remaining scope and revised costs, and engage a replacement contractor to complete Package one. Mr Mohwasa said completion of the first package would pave the way for implementation of Package two, subject to approved arrangements and availability of funding.
He reaffirmed government’s commitment to completing the project, saying priority would be given to resolving outstanding legal and contractual issues, establishing the resources required and resuming implementation in a lawful and financially responsible manner. ENDS