Exactly 181 relocation beneficiaries still await compensation
18 Nov 2026
At least 181 beneficiaries of the Maun International Airport relocation project are still awaiting compensation, with the Ministry of Transport and Infrastructure seeking an additional P8.3 million to settle outstanding claims.
Assistant Minister of Transport and Infrastructure, Mr Letlhogonolo Barongwang said the ministry was finalising a project memorandum to request P8,377,938.20 to compensate the remaining 154 beneficiaries whose payments were yet to be made.
Responding to a question in Parliament from Maun East Member of Parliament, Mr Goretetse Kekgonegile, Mr Barongwang said the assessment of properties affected by the relocation was completed in November 2005, with reports received by the then Department of Civil Aviation in May 2006 from the Department of Lands.
He said beneficiary payments commenced in November 2006 and that the project had 1 477 beneficiaries, who were relocated to Disaneng. Mr Barongwang explained that an internal audit conducted by the then Ministry of Transport and Communications in 2017 identified 297 beneficiaries who were still owed compensation.
Of these, 116 have since been paid through the Office of the Master of the High Court, leaving 181 outstanding beneficiaries. Of the outstanding claims, 27 are to be settled through the Master of the High Court, while 154 are to be paid by the ministry.
He attributed the delays to several challenges, including the deaths of some beneficiaries, difficulties in retrieving records from the Department of Lands in Francistown and Tawana Land Board, and challenges in tracing beneficiaries who had relocated from Maun.
Other factors included insufficient funds, prolonged consultations among stakeholders and some beneficiaries’ failure to meet Know Your Customer (KYC) requirements, resulting in payments being withheld.
Mr Barongwang said consultations involving Tawana Land Board, the Ministry of Lands and Agriculture, Civil Aviation Authority of Botswana and the Office of the Master of the High Court were ongoing to expedite the outstanding matters.
He urged beneficiaries to fulfil the required KYC procedures, saying the ministry and CAAB had engaged them on the matter.
He said the payment date would depend on approval of the project memorandum seeking additional funding.
Regarding payments through the Office of the Master of the High Court, he said 143 beneficiaries had been referred for payment, of whom 116 had been paid, while 27 remained outstanding. He explained that some of the pending claims involved minors, while other beneficiaries had not submitted applications to claim their entitlement. ENDS
Source : BOPA
Author : BOPA
Location : Gaborone
Event : Parliament
Date : 18 Nov 2026